← Back to track

Print Mode

Quick select
Show fields
Options
Layout
1

Save your content as an A5 PDF first. In the print dialog, choose "Save as PDF".

2

Select the saved PDF below. It will be rearranged into booklet page order and downloaded automatically.

Power Systems Fundamentals

8 sections · 31 topics · 146 concepts

eee-roadmap.muhammadhazimiyusri.uk/roadmaps/power-system-fundamentals/

Select items from the sidebar to preview them here.

Power Network Basics

Busbars, Nodes, and Branches

Foundation concepts for understanding power system structure. Covers the building blocks of power networks: nodes as connection points, branches as circuit elements, and busbars as central distribution points.

Prerequisites: AC Circuit Analysis, Complex numbers (phasors)
You'll learn to:
  • Identify nodes, branches, and loops in power network diagrams
  • Apply Kirchhoff's laws to power circuits
  • Convert circuit diagrams to graph representations
Node (Bus)

Common connection point where circuit elements meet, characterized by voltage phasor.

In power systems, each node has:

  • Voltage magnitude ∣V∣|V|∣V∣
  • Voltage angle θ\thetaθ
Branch

Circuit element connecting two nodes with impedance:

Z=R+jXZ = R + jXZ=R+jX

Examples: transmission lines, transformers, cables.

Busbar

Non-impedant conductive bar serving as central power distribution point in substations.

Busbar arrangement

Image: Wikimedia Commons, Public Domain

Kirchhoff's Laws

KCL (Current Law): Sum of currents entering a node equals sum leaving.

KVL (Voltage Law): Sum of voltages around any closed loop equals zero.

Resources:
  • MIT OCW 6.061 - Electric Power Systems https://ocw.mit.edu/courses/6-061-introduction-to-electric-power-systems-spring-2011/
  • NPTEL Power System Engineering https://nptel.ac.in/courses/108105104

Radial vs Ring vs Mesh Networks

Power distribution network configurations and their trade-offs. Understanding when to use radial (simple/cheap), ring (reliable), or mesh (redundant) topologies for different applications.

Prerequisites: Busbars, Nodes, and Branches
You'll learn to:
  • Classify network topologies from single-line diagrams
  • Evaluate trade-offs between reliability, cost, and complexity
  • Select appropriate topology for different applications
Radial Topology

Tree-shaped network with single path from source to consumer.

Pros: Simple, lowest cost, easy protection Cons: No redundancy - single fault causes outage Use: Rural areas, residential distribution

Ring Topology

Closed loop providing two alternative paths.

Can be operated as:

  • Open ring: One point normally open (like two radials)
  • Closed ring: Full loop energized (better reliability)

Use: Urban distribution, commercial areas

Mesh Topology

Multiple interconnections creating redundant paths.

Pros: Highest reliability, load sharing Cons: Complex protection, highest cost Use: Transmission networks, critical industrial loads

Resources:
  • Practical Engineering - How the Power Grid Works https://practical.engineering/
  • Electricity Grid Schematic (Wikimedia) https://commons.wikimedia.org/wiki/File:Electricity_Grid_Schematic_English.svg

Single Line Diagrams

Reading and interpreting single-line diagrams (SLDs), the standard representation for three-phase power systems. Covers symbols, conventions, and information typically shown.

Prerequisites: Network Topologies
You'll learn to:
  • Interpret single-line diagrams and identify all components
  • Understand standard electrical symbols (IEEE/IEC)
  • Trace power flow paths through systems
SLD Purpose

Simplified representation showing three-phase system as single line.

Why simplify? Three phases are balanced in normal operation, so one line represents all three.

Example SLD

Image: Wikimedia Commons, CC BY-SA 3.0

Reading Convention

Standard approach:

  1. Start at top (highest voltage)
  2. Work down to lowest voltage
  3. Left-to-right for same voltage level
Common Symbols
Symbol Component
Circle with ~ Generator
Two coils Transformer
Square with X Circuit breaker
Heavy horizontal line Busbar
Resources:
  • Learn to Interpret SLDs - EEP https://electrical-engineering-portal.com/learn-to-interpret-single-line-diagram
  • IEEE/IEC Electrical Symbols (Wikimedia) https://commons.wikimedia.org/wiki/Category:DIN_circuit_symbols

Power Flow Fundamentals

Active Power (P) and Reactive Power (Q)

Understanding the two components of AC power: real power that does useful work, and reactive power that maintains magnetic fields. Essential for power system analysis and equipment sizing.

Prerequisites: Single Line Diagrams, AC Circuit Analysis
You'll learn to:
  • Calculate P, Q, and S for single and three-phase systems
  • Explain physical significance of reactive power
  • Construct and interpret power triangles
Active Power (P)

Real power doing useful work (motors, heating, lighting).

Units: Watts (W, kW, MW)

P=V⋅I⋅cos⁡(ϕ)P = V \cdot I \cdot \cos(\phi)P=V⋅I⋅cos(ϕ)

For three-phase:

P3ϕ=3⋅VLL⋅I⋅cos⁡(ϕ)P_{3\phi} = \sqrt{3} \cdot V_{LL} \cdot I \cdot \cos(\phi)P3ϕ​=3​⋅VLL​⋅I⋅cos(ϕ)

Reactive Power (Q)

Power that oscillates between source and load, maintaining magnetic/electric fields.

Units: Volt-Amperes Reactive (VAR, kVAR, MVAR)

Q=V⋅I⋅sin⁡(ϕ)Q = V \cdot I \cdot \sin(\phi)Q=V⋅I⋅sin(ϕ)

  • Inductors (motors, transformers): Consume Q (lagging)
  • Capacitors: Supply Q (leading)
Apparent Power (S)

Vector sum of P and Q - total power the system must deliver.

Units: Volt-Amperes (VA, kVA, MVA)

S=P+jQS = P + jQS=P+jQ

∣S∣=P2+Q2|S| = \sqrt{P^2 + Q^2}∣S∣=P2+Q2​

Power Triangle

Graphical representation relating P, Q, and S: Power triangle

Image: Wikimedia Commons, CC BY-SA 3.0

  • Horizontal: Active power P
  • Vertical: Reactive power Q
  • Hypotenuse: Apparent power S
  • Angle φ: Power factor angle
Resources:
  • The Engineering Mindset - AC Power https://theengineeringmindset.com/electrical/
  • Khan Academy - AC Circuit Analysis https://www.khanacademy.org/science/physics/circuits-topic

Power Factor

The ratio of real to apparent power, indicating how effectively electrical power is being used. Critical for efficiency, billing, and equipment sizing.

Prerequisites: Active and Reactive Power
You'll learn to:
  • Calculate power factor from circuit measurements
  • Determine if power factor is leading or lagging
  • Design power factor correction using capacitors
Power Factor Definition

Ratio of real power to apparent power:

PF=PS=cos⁡(ϕ)PF = \frac{P}{S} = \cos(\phi)PF=SP​=cos(ϕ)

  • PF = 1.0 (unity): Pure resistive, V and I in phase
  • PF = 0: Pure reactive, no real power transferred
  • Typical industrial: 0.7 - 0.9 lagging
Leading vs Lagging

Describes current relative to voltage:

  • Lagging PF: Current lags voltage (inductive loads - motors)
  • Leading PF: Current leads voltage (capacitive loads)

Memory aid: ELI the ICE man

  • ELI: Voltage (E) leads Current (I) in Inductors (L)
  • ICE: Current (I) leads Voltage (E) in Capacitors (C)
Power Factor Correction

Adding capacitors to cancel inductive reactive power:

QC=P⋅(tan⁡ϕ1−tan⁡ϕ2)Q_C = P \cdot (\tan\phi_1 - \tan\phi_2)QC​=P⋅(tanϕ1​−tanϕ2​)

Where:

  • ϕ1\phi_1ϕ1​ = original PF angle
  • ϕ2\phi_2ϕ2​ = target PF angle

Target: PF > 0.95 to avoid utility penalties

Resources:
  • Power Factor Explained - Engineering Mindset https://theengineeringmindset.com/electrical/
  • Power Factor Diagram (Wikimedia) https://commons.wikimedia.org/wiki/Special:FilePath/Power_Factor_General_Case.svg

Voltage Levels and Transformation

Why power systems use different voltage levels and how transformers enable efficient power transfer. Understanding the hierarchy from generation through transmission to distribution.

Prerequisites: Power Factor
You'll learn to:
  • Identify voltage level classifications and their applications
  • Explain rationale for voltage transformation
  • Calculate power losses at different voltage levels
Voltage Classifications
Classification Voltage Range Application
Low Voltage (LV) Up to 1 kV Residential, commercial
Medium Voltage (MV) 1 - 35 kV Distribution, industrial
High Voltage (HV) 35 - 230 kV Sub-transmission
Extra High (EHV) 230 - 765 kV Bulk transmission
Why Transform Voltage

Power loss in transmission:

Ploss=I2RP_{loss} = I^2 RPloss​=I2R

For fixed power P=V⋅IP = V \cdot IP=V⋅I, doubling voltage halves current, reducing losses to one quarter.

Example: 100 MW at 400 kV vs 11 kV

  • At 400 kV: I = 144 A
  • At 11 kV: I = 5,249 A (36× higher losses!)
System Hierarchy

Typical power flow path:

  1. Generation (11-25 kV)
  2. Step-up to transmission (275-400 kV)
  3. Transmission (bulk power transfer)
  4. Step-down to sub-transmission (132 kV)
  5. Distribution (33 kV → 11 kV → 400 V)
  6. Consumer (400 V three-phase / 230 V single-phase)
Resources:
  • MIT OCW - Power System Structure https://ocw.mit.edu/courses/6-061-introduction-to-electric-power-systems-spring-2011/

Per-Unit System

Expressing electrical quantities as fractions of base values to simplify calculations across different voltage levels. Essential skill for all power system analysis.

Prerequisites: Voltage Levels
You'll learn to:
  • Select appropriate base values for power system analysis
  • Convert between actual and per-unit quantities
  • Perform change-of-base calculations
Per-Unit Basics

Quantities expressed as dimensionless fractions of base values:

Xpu=XactualXbaseX_{pu} = \frac{X_{actual}}{X_{base}}Xpu​=Xbase​Xactual​​

Advantages:

  • Transformer impedances same on both sides
  • Equipment values fall in narrow range (0.05-0.15 pu)
  • Simplifies hand calculations
Base Selection

Choose two independent bases (typically):

  • SbaseS_{base}Sbase​ = 100 MVA (industry standard)
  • VbaseV_{base}Vbase​ = Nominal system voltage at each level

Derived bases:

Ibase=Sbase3⋅VbaseI_{base} = \frac{S_{base}}{\sqrt{3} \cdot V_{base}}Ibase​=3​⋅Vbase​Sbase​​

Zbase=Vbase2SbaseZ_{base} = \frac{V_{base}^2}{S_{base}}Zbase​=Sbase​Vbase2​​

Per-Unit Conversion

Converting actual impedance to per-unit:

Zpu=Zactual⋅SbaseVbase2Z_{pu} = Z_{actual} \cdot \frac{S_{base}}{V_{base}^2}Zpu​=Zactual​⋅Vbase2​Sbase​​

Example: 10 Ω line at 11 kV on 100 MVA base

Zbase=112100=1.21 ΩZ_{base} = \frac{11^2}{100} = 1.21 \text{ Ω}Zbase​=100112​=1.21 Ω

Zpu=101.21=8.26 puZ_{pu} = \frac{10}{1.21} = 8.26 \text{ pu}Zpu​=1.2110​=8.26 pu

Change of Base

Converting between different bases:

Zpu,new=Zpu,old⋅Sbase,newSbase,old⋅(Vbase,oldVbase,new)2Z_{pu,new} = Z_{pu,old} \cdot \frac{S_{base,new}}{S_{base,old}} \cdot \left(\frac{V_{base,old}}{V_{base,new}}\right)^2Zpu,new​=Zpu,old​⋅Sbase,old​Sbase,new​​⋅(Vbase,new​Vbase,old​​)2

Used when combining equipment with different nameplate bases.

Resources:
  • Per-Unit System - Open Electrical https://openelectrical.org/index.php?title=Per-unit_System
  • NPTEL - Per Unit Calculations https://nptel.ac.in/courses/108105104

Load Flow Analysis

What is Load Flow Analysis

Numerical calculation of steady-state voltages, currents, and power flows throughout a network. The most fundamental power system study, used for planning, operations, and as input to other analyses.

Prerequisites: Per-Unit System
You'll learn to:
  • Set up a load flow problem with correct bus classifications
  • Understand purpose and applications of power flow studies
  • Identify inputs and outputs of load flow analysis
Load Flow Purpose

Answers the question: "Given generation and load, what are the voltages and power flows?"

Calculates:

  • Voltage magnitude and angle at each bus
  • Real and reactive power flow in each branch
  • System losses
  • Equipment loading (% of rating)
Bus Types

Each bus must be classified for the solver:

Type Known Unknown Purpose
Slack (Swing) V, θ P, Q Reference bus, balances system
PV (Generator) P, V Q, θ Voltage-controlled generation
PQ (Load) P, Q V, θ Most buses - loads and fixed gen

Typically: 1 slack, few PV, many PQ buses.

Applications
  • Planning: Assess new generation/transmission options
  • Operations: Real-time monitoring and control
  • Contingency (N-1): What if a line/generator trips?
  • Voltage assessment: Find weak points needing reactive support
  • Loss calculation: Optimize power flow paths
Resources:
  • MIT OCW - Power Flow Analysis https://ocw.mit.edu/courses/6-061-introduction-to-electric-power-systems-spring-2011/
  • PowerWorld Simulator (Free 13-bus) https://www.powerworld.com/products/simulator

Newton-Raphson and Gauss-Seidel Methods

The two main iterative algorithms for solving load flow equations. Gauss-Seidel is simpler but slower; Newton-Raphson is the industry standard for its speed and robustness.

Prerequisites: What is Load Flow Analysis
You'll learn to:
  • Explain conceptual differences between G-S and N-R methods
  • Understand why N-R is preferred for large systems
  • Interpret convergence behavior and potential issues
Why Iterative?

Load flow equations are nonlinear (power = V × I, but I depends on V).

No closed-form solution exists for networks with more than a few buses.

Must iterate: guess → calculate → refine → repeat until converged.

Gauss-Seidel Method

Sequential update of each bus voltage:

Vi(k+1)=1Yii[Pi−jQiVi(k)∗−∑j≠iYijVj(k)]V_i^{(k+1)} = \frac{1}{Y_{ii}} \left[ \frac{P_i - jQ_i}{V_i^{(k)*}} - \sum_{j \neq i} Y_{ij} V_j^{(k)} \right]Vi(k+1)​=Yii​1​​Vi(k)∗​Pi​−jQi​​−j=i∑​Yij​Vj(k)​​

Pros: Simple to understand and code

Cons: Slow (100+ iterations), poor convergence for large/meshed networks

Use: Small systems, educational purposes

Newton-Raphson Method

Solves power mismatch equations using Jacobian matrix:

[ΔPΔQ]=J[ΔθΔV]\begin{bmatrix} \Delta P \\ \Delta Q \end{bmatrix} = \mathbf{J} \begin{bmatrix} \Delta \theta \\ \Delta V \end{bmatrix}[ΔPΔQ​]=J[ΔθΔV​]

Jacobian structure:

J=[∂P∂θ∂P∂V∂Q∂θ∂Q∂V]\mathbf{J} = \begin{bmatrix} \frac{\partial P}{\partial \theta} & \frac{\partial P}{\partial V} \\ \frac{\partial Q}{\partial \theta} & \frac{\partial Q}{\partial V} \end{bmatrix}J=[∂θ∂P​∂θ∂Q​​∂V∂P​∂V∂Q​​]

Pros: Fast (3-5 iterations), robust, industry standard

Cons: More complex, requires Jacobian calculation

Fast Decoupled Method

Simplification of N-R exploiting natural decoupling:

  • P-θ: Real power strongly coupled to angles
  • Q-V: Reactive power strongly coupled to voltages

Solves two smaller systems instead of one large one. Even faster for transmission networks.

Convergence

Converged: Mismatches below tolerance (typically 0.001 pu)

Divergence causes:

  • Poor initial guess (use flat start: V=1.0, θ=0)
  • Excessive reactive demand
  • Islanded sections
  • Negative impedance (modelling error)
Resources:
  • NPTEL - Load Flow Methods https://nptel.ac.in/courses/108105067
  • Pandapower (Python library) https://www.pandapower.org/

Interpreting Load Flow Results

How to read and analyze load flow outputs: voltage profiles, line loadings, losses, and reactive power flows. Identifying problems and potential solutions.

Prerequisites: Newton-Raphson and Gauss-Seidel Methods
You'll learn to:
  • Analyze voltage profiles and identify violations
  • Identify overloaded elements from load flow results
  • Calculate and interpret system losses
Voltage Profile

Plot of voltage magnitude across buses, typically ordered by electrical distance from source.

Acceptable range: Usually 0.95 - 1.05 pu (±5%)

Violations indicate:

  • Heavy loading (voltage drop)
  • Insufficient reactive support
  • Need for tap changer adjustment or capacitor banks
Branch Loading

Power flow as percentage of thermal rating:

Loading=∣Sflow∣Srating×100%\text{Loading} = \frac{|S_{flow}|}{S_{rating}} \times 100\%Loading=Srating​∣Sflow​∣​×100%

Watch for:

  • >80% - approaching limit, monitor closely
  • >100% - overloaded, requires action

Heavily loaded lines are bottlenecks limiting power transfer.

System Losses

Total real power losses:

Ploss=∑Pgeneration−∑PloadP_{loss} = \sum P_{generation} - \sum P_{load}Ploss​=∑Pgeneration​−∑Pload​

Typical values: 2-8% of total generation

Loss breakdown:

  • Transmission: ~2-3%
  • Distribution: ~4-6%

High losses indicate inefficient power flow paths.

Reactive Power Flow

Shows where Q is generated and consumed.

Key observations:

  • Generators at Q limits? May need more reactive support
  • Long lines consuming Q? Consider series compensation
  • Transformers with high Q flow? Check tap positions
Results Table Example

Typical load flow output:

Bus V (pu) θ (°) P (MW) Q (MVAR)
1 (Slack) 1.000 0.0 150.2 45.3
2 (PV) 1.020 -2.1 80.0 23.1
3 (PQ) 0.985 -4.5 -50.0 -20.0

Negative P/Q = load consuming power

Resources:
  • OpenDSS - Distribution System Simulator https://sourceforge.net/projects/electricdss/
  • MATPOWER (MATLAB) https://matpower.org/

Fault Analysis

Types of Faults

Classification of short circuit faults in power systems: three-phase, single line-to-ground, line-to-line, and double line-to-ground. Understanding fault severity and frequency of occurrence.

Prerequisites: Interpreting Load Flow Results
You'll learn to:
  • Classify fault types from descriptions and diagrams
  • Explain which faults are most severe and most common
  • Understand sequence network connections for each fault type
Three-Phase Fault (LLL)

All three phases short-circuited together (with or without ground).

Three-phase fault

Image: Wikimedia Commons, CC BY-SA 3.0

  • Severity: Most severe (highest current)
  • Frequency: Rarest (~5% of faults)
  • Analysis: Simplest - system remains balanced, only positive sequence needed
Single Line-to-Ground (SLG)

One phase contacts ground.

  • Severity: Depends on grounding (can exceed 3-phase in solidly grounded systems)
  • Frequency: Most common (~70-80% of faults)
  • Analysis: Requires all three sequence networks in series

Common causes: Lightning, tree contact, insulator flashover

Line-to-Line Fault (LL)

Two phases short-circuited together (not involving ground).

  • Severity: ~87% of three-phase fault current
  • Frequency: ~15-20% of faults
  • Analysis: Positive and negative sequence networks in parallel
Double Line-to-Ground (LLG)

Two phases short-circuited together and to ground.

  • Severity: Can exceed three-phase in some cases
  • Frequency: ~5-10% of faults
  • Analysis: Most complex - all sequences in parallel
Fault Severity Ranking

For solidly grounded systems (typical UK distribution):

I3ϕ>ISLG>ILLG>ILLI_{3\phi} > I_{SLG} > I_{LLG} > I_{LL}I3ϕ​>ISLG​>ILLG​>ILL​

For impedance grounded systems:

I3ϕ>ILLG>ILL>ISLGI_{3\phi} > I_{LLG} > I_{LL} > I_{SLG}I3ϕ​>ILLG​>ILL​>ISLG​

Three-phase fault is usually used for equipment rating as it's the worst case.

Resources:
  • Circuit Globe - Symmetrical and Unsymmetrical Faults https://circuitglobe.com/symmetrical-and-unsymmetrical-faults.html

Symmetrical Components Theory

Mathematical technique to analyze unbalanced conditions by decomposing into three balanced systems: positive, negative, and zero sequence. Essential for unbalanced fault calculations.

Prerequisites: Types of Faults
You'll learn to:
  • Convert between phase and sequence quantities
  • Draw sequence networks for system components
  • Apply correct sequence network connections for different faults
Why Symmetrical Components?

Unbalanced three-phase systems are difficult to analyze directly.

Solution: Decompose into three balanced systems that can be analyzed independently, then recombine.

Invented by Charles Fortescue (1918).

The Three Sequences

Symmetrical components

Image: Wikimedia Commons, CC BY-SA 4.0

Positive sequence (1): ABC rotation (normal operating condition)

  • Generators produce only positive sequence EMF

Negative sequence (2): ACB rotation (reverse)

  • Created by unbalanced conditions
  • Causes heating in machines

Zero sequence (0): All three phasors in phase

  • Represents ground return current
  • Only flows if there's a ground path
The 'a' Operator

Complex operator that rotates by 120°:

a=1∠120°=−0.5+j0.866a = 1 \angle 120° = -0.5 + j0.866a=1∠120°=−0.5+j0.866

a2=1∠240°=−0.5−j0.866a^2 = 1 \angle 240° = -0.5 - j0.866a2=1∠240°=−0.5−j0.866

a3=1a^3 = 1a3=1

1+a+a2=01 + a + a^2 = 01+a+a2=0

Transformation Equations

Phase to sequence:

[V0V1V2]=13[1111aa21a2a][VaVbVc]\begin{bmatrix} V_0 \\ V_1 \\ V_2 \end{bmatrix} = \frac{1}{3} \begin{bmatrix} 1 & 1 & 1 \\ 1 & a & a^2 \\ 1 & a^2 & a \end{bmatrix} \begin{bmatrix} V_a \\ V_b \\ V_c \end{bmatrix}​V0​V1​V2​​​=31​​111​1aa2​1a2a​​​Va​Vb​Vc​​​

Sequence to phase:

[VaVbVc]=[1111a2a1aa2][V0V1V2]\begin{bmatrix} V_a \\ V_b \\ V_c \end{bmatrix} = \begin{bmatrix} 1 & 1 & 1 \\ 1 & a^2 & a \\ 1 & a & a^2 \end{bmatrix} \begin{bmatrix} V_0 \\ V_1 \\ V_2 \end{bmatrix}​Va​Vb​Vc​​​=​111​1a2a​1aa2​​​V0​V1​V2​​​

Sequence Network Connections

For each fault type, connect sequence networks differently:

Fault Connection
3-phase Positive only
SLG All three in series
LL Positive & negative in parallel
LLG All three in parallel
Resources:
  • SEL - Symmetrical Components Tutorial https://selinc.com/api/download/100688
  • NPTEL - Symmetrical Components https://nptel.ac.in/courses/108105067

Fault Levels and Short Circuit Calculations

Calculating fault current magnitude using per-unit and MVA methods. Results used for equipment selection, protection settings, and arc flash studies.

Prerequisites: Symmetrical Components Theory
You'll learn to:
  • Calculate fault levels using MVA and per-unit methods
  • Select appropriate equipment ratings based on fault levels
  • Understand relationship between impedance and fault current
Fault Level Definition

Maximum power (MVA) or current (kA) that flows during a fault at a given point.

Two expressions:

Fault MVA=SbaseZpu\text{Fault MVA} = \frac{S_{base}}{Z_{pu}}Fault MVA=Zpu​Sbase​​

Fault kA=Fault MVA3×kV\text{Fault kA} = \frac{\text{Fault MVA}}{\sqrt{3} \times kV}Fault kA=3​×kVFault MVA​

Per-Unit Method

For three-phase fault at a bus:

If(pu)=Vpre−faultZtotalI_f (pu) = \frac{V_{pre-fault}}{Z_{total}}If​(pu)=Ztotal​Vpre−fault​​

Usually assume Vpre−fault=1.0V_{pre-fault} = 1.0Vpre−fault​=1.0 pu.

Example: If total impedance to fault = 0.1 pu:

If=1.00.1=10 puI_f = \frac{1.0}{0.1} = 10 \text{ pu}If​=0.11.0​=10 pu

MVA Method

Quick calculation without per-unit conversion:

Series impedances: 1MVAtotal=1MVA1+1MVA2\frac{1}{MVA_{total}} = \frac{1}{MVA_1} + \frac{1}{MVA_2}MVAtotal​1​=MVA1​1​+MVA2​1​

Parallel sources: MVAtotal=MVA1+MVA2MVA_{total} = MVA_1 + MVA_2MVAtotal​=MVA1​+MVA2​

Example:

  • Grid infeed: 500 MVA
  • Transformer: 10% on 20 MVA base → 200.1=200\frac{20}{0.1} = 2000.120​=200 MVA

1MVAf=1500+1200\frac{1}{MVA_f} = \frac{1}{500} + \frac{1}{200}MVAf​1​=5001​+2001​

MVAf=143 MVAMVA_f = 143 \text{ MVA}MVAf​=143 MVA

X/R Ratio

Ratio of reactance to resistance in fault path.

Importance:

  • Determines DC offset decay rate
  • Affects peak asymmetrical current
  • Higher X/R → slower decay → higher peak

Typical values:

  • Transmission: X/R = 15-30
  • Distribution: X/R = 5-15
  • LV systems: X/R = 2-5
Making vs Breaking Current

Making current: Peak asymmetrical (first half-cycle)

Ipeak=Isym×2×(1+e−RXπ)I_{peak} = I_{sym} \times \sqrt{2} \times (1 + e^{-\frac{R}{X}\pi})Ipeak​=Isym​×2​×(1+e−XR​π)

Breaking current: RMS symmetrical (after few cycles)

Circuit breakers rated for both values.

Resources:
  • Arc Advisor - MVA to kA Conversion https://arcadvisor.com/legacy/mva-ka-conversion

Why Fault Analysis Matters

Applications of fault studies in equipment selection, protection design, safety assessment, and system planning. Understanding how fault levels impact every aspect of power system design.

Prerequisites: Fault Levels and Short Circuit Calculations
You'll learn to:
  • Explain importance of fault analysis for safety and equipment
  • Relate fault levels to protection coordination
  • Understand impact of DG on fault levels
Equipment Rating

All equipment must withstand fault conditions:

Equipment Fault Rating Needed
Circuit breakers Breaking & making capacity
Busbars Short-time withstand (1-3 sec)
Cables Short-circuit rating
CTs Thermal & dynamic limits

Under-rated equipment can fail catastrophically during faults.

Protection Design

Relay settings require accurate fault currents:

  • Pick-up settings: Must detect minimum fault current
  • Time grading: Based on fault magnitude variation
  • Reach settings: Distance relays need accurate impedances

Wrong fault data = wrong protection = nuisance trips or failure to operate.

Arc Flash Safety

Arc flash energy proportional to fault current and duration:

E=I1.081×t×kE = I^{1.081} \times t \times kE=I1.081×t×k

Higher fault level → higher incident energy → more PPE required.

IEEE 1584 standard requires fault study for arc flash assessment.

Impact of Distributed Generation

Adding DG increases fault levels:

  • Synchronous generators: Contribute 4-6× rated current
  • Inverter-based (solar/wind): Limited to 1.1-1.5× rated

Existing equipment may become under-rated when DG added.

Re-assessment required for any new generation connection.

Standards

Key fault calculation standards:

  • IEC 60909: International standard, uses voltage factors
  • IEEE C37 series: North American practice
  • ENA G74: UK-specific for DG connections

IPSA supports IEC 60909 and multiple other methods.

Resources:
  • Coursera - Power System Protection https://www.coursera.org/specializations/power-system-generation-transmission-and-protection

Protection Fundamentals

Protection System Principles

The fundamental requirements of power system protection: speed, selectivity, sensitivity, and reliability. Understanding how protection systems detect faults and isolate them.

Prerequisites: Why Fault Analysis Matters
You'll learn to:
  • Explain the four key requirements of protection systems
  • Understand basic protection system components
  • Describe the protection chain from detection to isolation
Purpose of Protection

Detect abnormal conditions and isolate faulted equipment to:

  • Protect people from electric shock and arc flash
  • Limit equipment damage by clearing faults quickly
  • Maintain system stability by preventing cascade failures
  • Minimize outage extent by isolating only faulted section
The Four S's

Speed: Clear faults quickly (typically <100ms for transmission)

  • Limits equipment damage
  • Reduces arc flash energy
  • Maintains stability

Selectivity: Only trip the minimum necessary equipment

  • Also called "discrimination"
  • Faulted section isolated, rest remains energized

Sensitivity: Detect all faults, even low-magnitude ones

  • Must see minimum fault current
  • Balance with security (avoid nuisance trips)

Security/Reliability: Operate when required, not otherwise

  • Dependability: Will operate for genuine faults
  • Security: Won't operate for external faults or load
Protection System Components

Protection relay panel

Image: Wtshymanski, Wikimedia Commons, CC BY-SA 3.0

CT (Current Transformer): Measures current, isolates relay from HV

VT (Voltage Transformer): Measures voltage, provides isolation

Relay: Processes CT/VT signals, makes trip decision

Circuit Breaker: Interrupts fault current

DC Supply: Battery-backed power for relays and trip coils

Protection Chain

Fault → CT/VT detect → Relay processes → Trip signal → Breaker opens

Typical times:

  • Relay operation: 20-40 ms
  • Breaker operation: 40-80 ms
  • Total clearance: 60-120 ms (transmission)
  • Distribution: up to 500 ms+ (for coordination)
Resources:
  • NPTEL - Power System Protection https://nptel.ac.in/courses/108105104

Protection Relay Types

The main types of protection relays: overcurrent, distance, and differential. Understanding operating principles and applications for each type.

Prerequisites: Protection System Principles
You'll learn to:
  • Explain operating principle of each relay type
  • Select appropriate relay type for different applications
  • Understand ANSI device numbering system
Overcurrent Relays (50/51)

Trips when current exceeds a threshold.

50 - Instantaneous: Fixed time, high pickup

  • Typically set to see close-in faults only
  • Operates in 20-50 ms

51 - Time Overcurrent: Inverse time characteristic

  • Higher current = faster operation
  • Allows coordination with downstream devices

Application: Distribution networks, motor protection, backup protection

IDMT Characteristics

Inverse Definite Minimum Time curves:

Time-current characteristic

Image: Wikimedia Commons, CC BY-SA 4.0

t=TMS×k(I/Is)α−1t = \frac{TMS \times k}{(I/I_s)^\alpha - 1}t=(I/Is​)α−1TMS×k​

Where:

  • TMS = Time Multiplier Setting
  • IsI_sIs​ = Pick-up current setting
  • k, α = curve constants
Curve k α
Standard Inverse (SI) 0.14 0.02
Very Inverse (VI) 13.5 1.0
Extremely Inverse (EI) 80 2.0

VI/EI used where fault current varies significantly with location.

Distance Relays (21)

Measures impedance (Z = V/I) to determine fault location.

Zones:

  • Zone 1: 80-85% of line, instantaneous
  • Zone 2: 100-120% of line, ~0.3s delay
  • Zone 3: 150-200%, backup, ~1s delay

Application: Transmission line protection

Differential Relays (87)

Compares current entering vs leaving protected zone.

Ioperate=∣Iin−Iout∣I_{operate} = |I_{in} - I_{out}|Ioperate​=∣Iin​−Iout​∣

If difference exceeds threshold → internal fault → trip.

Key property: 100% selective - only operates for internal faults

Applications:

  • Transformer (87T)
  • Generator (87G)
  • Busbar (87B)
  • Motor (87M)
ANSI Device Numbers

Standard numbering for protection functions:

Number Function
21 Distance
25 Synch check
27 Undervoltage
50 Instantaneous OC
51 Time OC
59 Overvoltage
67 Directional OC
81 Frequency
87 Differential

Suffix letters: N=neutral, G=ground, T=transformer

Resources:
  • PAC Basics - Protection Fundamentals https://pacbasics.org/
  • GE Multilin - Relay School https://www.gegridsolutions.com/multilin/

Protection Coordination

Designing protection systems so that only the device nearest the fault operates, minimizing the extent of the outage. Time grading, current grading, and coordination principles.

Prerequisites: Protection Relay Types
You'll learn to:
  • Design coordinated protection schemes
  • Calculate coordination time intervals
  • Select appropriate IDMT curve characteristics
Discrimination Principle

Goal: Only the device closest to the fault should operate.

If fault at point F:

Source ──[A]──[B]──[C]── F ──[Load]

Relay C should trip first. If C fails, B backs up. If B fails, A backs up.

Achieved through time grading and/or current grading.

Time Grading

Upstream devices have progressively longer delays.

Coordination Time Interval (CTI): 0.3 - 0.5 seconds

Accounts for:

  • Breaker operating time (~50-80 ms)
  • Relay overshoot (~50 ms)
  • Safety margin (~100 ms)

Example:

  • Relay C: 0.1s at max fault
  • Relay B: 0.1 + 0.4 = 0.5s
  • Relay A: 0.5 + 0.4 = 0.9s
Current Grading

Use fault current magnitude differences to discriminate.

Fault current decreases with distance from source due to line impedance.

Set instantaneous elements (50) to see only close-in faults:

Ipickup>Ifault,downstreamI_{pickup} > I_{fault,downstream}Ipickup​>Ifault,downstream​

Limitation: Doesn't work well on short feeders or where fault current doesn't vary much.

Grading Margin Calculation

For IDMT relays, check coordination at maximum fault current through both devices:

  1. Calculate downstream relay time at max fault
  2. Add CTI (0.3-0.5s)
  3. Calculate upstream TMS to achieve this time

TMSupstream=(tdownstream+CTI)×((I/Is)α−1)kTMS_{upstream} = \frac{(t_{downstream} + CTI) \times ((I/I_s)^\alpha - 1)}{k}TMSupstream​=k(tdownstream​+CTI)×((I/Is​)α−1)​

Coordination Challenges

Parallel feeders: Both see same fault current - need directional elements (67)

Ring networks: Fault current from both directions - need directional or differential

DG infeed: Changes fault current magnitude and direction

Motor contribution: Adds to fault current, decays quickly

Resources:
  • Coursera - Protection Coordination https://www.coursera.org/specializations/power-system-generation-transmission-and-protection

Time-Current Curves

Graphical representation of protection device characteristics. How to plot, read, and use TCCs for coordination studies.

Prerequisites: Protection Coordination
You'll learn to:
  • Construct and interpret TCC plots
  • Identify coordination margins and problems
  • Verify protection against equipment damage curves
TCC Basics

Log-log plot showing operating time vs current.

Axes:

  • X-axis: Current (log scale), usually in Amps
  • Y-axis: Time (log scale), in seconds

Why log-log? Covers wide ranges (0.01s to 1000s, 10A to 100kA)

Device Curves

Fuses: Show as bands (two lines)

  • Left line: Minimum melting time
  • Right line: Total clearing time

Relays: Show as single lines (adjustable)

  • Family of curves for different TMS settings

Breakers: Vertical lines at:

  • Continuous rating
  • Instantaneous trip (if equipped)
Coordination on TCCs

Rules for proper coordination:

  1. Downstream curve must be below and left of upstream
  2. Maintain CTI gap at all fault current levels
  3. Check at both minimum and maximum fault points

Crossover: Where curves intersect = loss of coordination

Damage Curves

Equipment withstand limits plotted on same TCC:

Cable damage curve: I2t=kI^2 t = kI2t=k Where k depends on conductor material and insulation

Transformer: Inrush point and thermal damage

Motor: Starting current and locked rotor time

Rule: Protective device curve must be left of damage curve (faster operation).

TCC Example

Reading a coordination study:

Time (s)
1000 |
 100 |          [Upstream Relay]
  10 |     [Downstream Relay]
   1 |  
 0.1 | [Fuse]
0.01 |_________________________
     10   100   1k   10k   Current (A)

Check gaps between curves at fault current levels.

Resources:
  • ETAP TCC Tutorial https://etap.com/

Protection Zones and Backup

Dividing the power system into protection zones with overlapping boundaries. Primary and backup protection philosophy to ensure no blind spots.

Prerequisites: Time-Current Curves
You'll learn to:
  • Define protection zones for power system components
  • Design primary and backup protection schemes
  • Understand zone overlap at circuit breakers
Zone Definition

A zone is an area of the network protected by a specific relay or set of relays.

Zone boundaries defined by CT locations.

Principle: Every element must be within at least one zone.

Zone Overlap

Zones should overlap at circuit breakers to avoid blind spots.

Zone A              Zone B
|<────────────>|<────────────>|
CT            CB            CT

Fault at CB location seen by both zones - both may trip (acceptable for reliability).

Primary Protection

First line of defense for a zone.

Characteristics:

  • Fast operation (instantaneous or Zone 1)
  • Highly selective (only for internal faults)
  • Examples: Differential (87), Distance Zone 1 (21)

Should clear ~90% of faults.

Backup Protection

Local backup: Duplicate protection within same zone

  • Same speed and selectivity as primary
  • Protects against relay/CT failure
  • Example: Dual main protections

Remote backup: Protection from adjacent zones

  • Slower (time-delayed)
  • Less selective (trips more than necessary)
  • Example: Distance Zone 2/3, time-graded overcurrent
Typical Protection Schemes
Equipment Primary Backup
Transmission line Distance (21) Distance Z2/Z3, OC
Transformer Differential (87T) Overcurrent (51), REF
Busbar Differential (87B) Breaker fail, remote
Generator Differential (87G) Overcurrent, loss of excitation
Motor Thermal (49), Diff Overcurrent (51)
Breaker Failure Protection

What if the breaker doesn't open?

Breaker Failure (50BF):

  1. Trip signal sent to breaker
  2. Timer starts (typically 150-200ms)
  3. If fault current still flowing → trip all adjacent breakers

Last resort backup - isolates larger area but prevents catastrophic failure.

Resources:
  • IEEE - Protection Zones https://ieeexplore.ieee.org/document/9640382/
  • Electrical Axis - Zones of Protection http://www.electricalaxis.com/

Network Components

Transformers in Power Networks

Power transformers for voltage transformation: ratings, impedance, tap changers, and vector groups. Understanding how transformer parameters affect load flow and fault studies.

Prerequisites: Protection Zones and Backup
You'll learn to:
  • Specify transformer ratings, impedances, and vector groups
  • Understand tap changer operation and voltage regulation
  • Calculate fault current contribution through transformers
Transformer Basics

Power transformer

Image: Wikimedia Commons, CC BY-SA 3.0

Voltage transformation by turns ratio:

V1V2=N1N2\frac{V_1}{V_2} = \frac{N_1}{N_2}V2​V1​​=N2​N1​​

Ratings specified:

  • MVA (apparent power)
  • Primary/secondary voltage (kV)
  • Impedance (%Z on rating)
  • Vector group
Transformer Impedance

Impedance limits fault current and causes voltage drop.

Typical values:

  • Distribution (11/0.4kV): 4-6%
  • Primary (33/11kV): 7-10%
  • Transmission (132/33kV): 10-15%

Fault current through transformer:

Ifault=100Z%×IratedI_{fault} = \frac{100}{Z\%} \times I_{rated}Ifault​=Z%100​×Irated​

Example: 10% impedance → fault current = 10× rated

Tap Changers

Adjust turns ratio to regulate voltage.

OLTC (On-Load Tap Changer):

  • Changes taps without interrupting load
  • Typical range: ±10% in 1.25% or 1.67% steps
  • Located on HV winding (lower current)
  • Automatic voltage regulation (AVR) control

Off-circuit tap changer:

  • Must de-energize to change
  • Used for fixed adjustment only
Vector Groups

Transformer vector groups

Image: Wikimedia Commons

Notation describes winding connections and phase shift.

Letters:

  • D/d = Delta
  • Y/y = Star (Wye)
  • N/n = Neutral brought out
  • Capital = HV, lowercase = LV

Number: Phase shift in clock hours (× 30°)

Common groups:

Group Shift Application
Dyn11 -30° Distribution
YNd1 +30° Generator step-up
Yy0 0° Auto-transformer
Parallel Operation

Transformers in parallel must have:

  1. Same vector group (or compatible: Dy1 with Dy1)
  2. Same voltage ratio (within tap range)
  3. Similar impedance (within 10% for load sharing)

Mismatched vector groups → circulating currents → overheating

Resources:
  • The Engineering Mindset - Electrical https://theengineeringmindset.com/electrical/
  • Electrical4U - Vector Groups https://www.electrical4u.com/vector-group-of-transformer/

Cables and Underground Lines

Power cable construction, impedance characteristics, current ratings, and voltage drop calculations. Derating factors for installation conditions.

Prerequisites: Transformers in Power Networks
You'll learn to:
  • Calculate cable sizing for ampacity and voltage drop
  • Apply derating factors for installation conditions
  • Understand cable impedance characteristics
Cable Construction

Cable cross-section

Image: Wikimedia Commons, CC BY-SA 3.0

Layers (inside out):

  1. Conductor (copper or aluminium)
  2. Conductor screen
  3. Insulation (XLPE, EPR, or PVC)
  4. Insulation screen
  5. Metallic sheath/screen
  6. Outer sheath (PE or PVC)

Insulation temperature limits:

  • XLPE: 90°C continuous, 250°C short-circuit
  • PVC: 70°C continuous
Cable Impedance

Cables have higher R/X ratio than overhead lines.

Typical values at 50Hz:

Cable R (Ω/km) X (Ω/km) R/X
LV 185mm² 0.164 0.073 2.2
11kV 185mm² 0.164 0.090 1.8
33kV 300mm² 0.060 0.110 0.5

High R/X ratio means voltage drop dominated by real power at LV.

Current Rating (Ampacity)

Maximum continuous current limited by:

  • Conductor temperature
  • Insulation thermal limits
  • Heat dissipation (installation method)

Base rating from manufacturer tables, then apply derating:

Irated=Ibase×K1×K2×K3×K4I_{rated} = I_{base} \times K_1 \times K_2 \times K_3 \times K_4Irated​=Ibase​×K1​×K2​×K3​×K4​

Derating Factors
Factor Description Typical Range
K1K_1K1​ Ambient temperature 0.7 - 1.1
K2K_2K2​ Grouping (multiple cables) 0.6 - 1.0
K3K_3K3​ Soil thermal resistivity 0.8 - 1.0
K4K_4K4​ Depth of burial 0.95 - 1.0

Example: 400A base × 0.9 × 0.7 × 0.95 × 0.98 = 235A

Voltage Drop Calculation

Three-phase voltage drop:

ΔV=3×I×L×(Rcos⁡ϕ+Xsin⁡ϕ)1000\Delta V = \frac{\sqrt{3} \times I \times L \times (R \cos\phi + X \sin\phi)}{1000}ΔV=10003​×I×L×(Rcosϕ+Xsinϕ)​

Where:

  • I = current (A)
  • L = length (m)
  • R, X = resistance, reactance (Ω/km)

UK limits (BS 7671):

  • Lighting: 3%
  • Other: 5%
  • Total from origin: 5%
Resources:
  • BS 7671 Cable Sizing Guide https://electrical.theiet.org/
  • Nexans Cable Calculator https://www.nexans.co.uk/

Overhead Lines

Transmission and distribution overhead line characteristics: impedance, thermal ratings, sag considerations, and comparison with cables.

Prerequisites: Cables and Underground Lines
You'll learn to:
  • Calculate overhead line impedance
  • Understand thermal rating methods (static vs dynamic)
  • Compare overhead lines with underground cables
Line Construction

Transmission tower

Image: Wikimedia Commons, CC BY-SA 4.0

Conductor types:

  • ACSR: Aluminium Conductor Steel Reinforced
  • AAAC: All Aluminium Alloy Conductor
  • HTLS: High Temperature Low Sag (for uprating)

Typical spans:

  • Distribution: 50-150m
  • Transmission: 300-500m
Line Impedance

Overhead lines have lower R/X ratio than cables.

Typical values (per km):

Line R (Ω/km) X (Ω/km) R/X
11kV distribution 0.3 0.35 0.9
33kV 0.12 0.38 0.3
132kV 0.06 0.40 0.15
400kV 0.03 0.32 0.1

Higher X due to wider conductor spacing (air insulation).

Thermal Ratings

Current limited by conductor temperature (sag limit or annealing).

Static rating: Conservative fixed value

  • Assumes: high ambient, full sun, low wind
  • Typically 50-75% of actual capacity

Dynamic Line Rating (DLR): Real-time calculation

  • Uses weather data (wind, ambient, solar)
  • Can increase capacity 10-30%
  • Requires monitoring equipment
Sag and Clearance

Conductor sag increases with:

  • Temperature (thermal expansion)
  • Current (resistive heating)
  • Ice loading (weight)

Sag formula (parabolic approximation):

S=wL28TS = \frac{wL^2}{8T}S=8TwL2​

Where:

  • w = weight per unit length
  • L = span length
  • T = conductor tension

Clearance requirements (to ground, buildings, other lines) set maximum allowable sag.

OHL vs Cable Comparison
Aspect Overhead Line Cable
Capital cost Lower (5-10×) Higher
Maintenance Higher Lower
Visual impact High None
Reliability Weather-affected Protected
Fault rate Higher Lower
Repair time Faster Slower
Reactive power Generates (line charging) Consumes
Urban use Limited Preferred
Resources:
  • US DOE - Dynamic Line Rating https://www.energy.gov/oe/articles/dynamic-line-rating-report-congress-june-2019
  • IEEE 738 - Line Rating Calculation https://standards.ieee.org/

Generators and Synchronous Machines

Synchronous generator characteristics, capability curves, and reactive power control. Understanding generator contribution to fault current and voltage regulation.

Prerequisites: Overhead Lines
You'll learn to:
  • Interpret generator capability curves
  • Understand excitation control and reactive power
  • Calculate generator fault current contribution
Synchronous Machine Basics

Synchronous generator

Image: Wikimedia Commons, Public Domain

Speed-frequency relationship:

f=P×N120f = \frac{P \times N}{120}f=120P×N​

Where:

  • f = frequency (Hz)
  • P = number of poles
  • N = speed (rpm)

For 50Hz: 2-pole = 3000rpm, 4-pole = 1500rpm

Generator Reactances

Multiple reactances for different timescales:

Reactance Symbol Typical (pu) Timescale
Sub-transient Xd′′X''_dXd′′​ 0.1-0.25 0-50ms
Transient Xd′X'_dXd′​ 0.15-0.35 50ms-2s
Synchronous XdX_dXd​ 1.0-2.5 Steady-state

Fault studies use Xd′′X''_dXd′′​ for maximum (initial) fault current.

Capability Curve

Generator capability curve

Image: Wikimedia Commons, CC BY-SA 4.0

P-Q diagram showing operating limits:

Limits:

  • Right arc: Armature current (MVA rating)
  • Top arc: Field current (over-excitation)
  • Bottom curve: Stator end heating (under-excitation)
  • Vertical line: Prime mover (MW limit)

Generator can operate anywhere inside the curve.

Excitation and Reactive Power

Field current controls reactive power output:

Over-excited: High field current → exports Q → supports voltage

Under-excited: Low field current → absorbs Q → may depress voltage

AVR (Automatic Voltage Regulator):

  • Maintains terminal voltage setpoint
  • Adjusts field current automatically
  • Droop setting for load sharing
Generator Control Modes

In load flow analysis:

PV mode (voltage control):

  • P and V specified
  • Q calculated (within limits)
  • Normal operation

PQ mode (fixed output):

  • P and Q both specified
  • V calculated
  • Used when at reactive limit

Slack bus:

  • V and θ specified (reference)
  • P and Q calculated
  • Balances system losses
Fault Current Contribution

Generator fault current decays over time:

If′′=E′′Xd′′I''_f = \frac{E''}{X''_d}If′′​=Xd′′​E′′​ (sub-transient, first few cycles)

If′=E′Xd′I'_f = \frac{E'}{X'_d}If′​=Xd′​E′​ (transient, up to ~2 seconds)

If=EXdI_f = \frac{E}{X_d}If​=Xd​E​ (steady-state, if fault sustained)

Typical contribution: 4-6× rated current initially

Resources:
  • NPTEL - Synchronous Machines https://nptel.ac.in/courses/108105017
  • All About Circuits - Synchronous Generators https://www.allaboutcircuits.com/

Distributed Generation

How Renewables Connect to the Grid

Grid connection architectures for solar PV and wind generation. Understanding inverter-based resources, transformer requirements, and connection voltage selection.

Prerequisites: Generators and Synchronous Machines
You'll learn to:
  • Describe grid connection architectures for solar and wind
  • Understand inverter-based resource characteristics
  • Select appropriate connection voltage for different capacities
Solar PV Connection

Solar PV array

Image: Wikimedia Commons, CC BY-SA 3.0

Connection chain:

PV Panels (DC) → Inverter (DC/AC) → Transformer → Grid

Inverter functions:

  • DC to AC conversion
  • Maximum Power Point Tracking (MPPT)
  • Grid synchronisation
  • Power factor control
  • Anti-islanding protection
Wind Turbine Connection

Wind turbine

Image: Arne Nordmann, Wikimedia Commons, CC BY-SA 2.5

Two main types:

DFIG (Doubly-Fed Induction Generator):

  • Partial converter (30% rating)
  • Limited fault ride-through
  • Older technology

Full Converter:

  • 100% power through converter
  • Better fault ride-through
  • Decoupled from grid frequency
  • Modern standard
Connection Voltage Selection

Voltage level based on capacity:

Capacity Typical Voltage Connection
<50 kW 400V (LV) Single premises
50kW - 1MW 400V or 11kV LV or HV feeder
1 - 10 MW 11kV or 33kV Primary substation
10 - 50 MW 33kV or 132kV BSP or GSP
>50 MW 132kV+ Transmission

DNO specifies minimum connection voltage in offer.

Inverter-Based Resources (IBR)

Key differences from synchronous machines:

Aspect Synchronous Inverter
Inertia Yes (rotating mass) No (virtual possible)
Fault current 4-6× rated 1.1-1.5× rated
Frequency response Inherent Programmed
Reactive capability Full range Limited by rating

Grid-forming vs Grid-following:

  • Grid-following: Needs grid voltage reference
  • Grid-forming: Can establish voltage/frequency (emerging)
Connection Equipment

Typical DG connection includes:

  • Inverter(s) with protection settings
  • LV switchboard with metering
  • Transformer (if HV connection)
  • HV switchgear (ring main unit or circuit breaker)
  • G99 protection relay (interface protection)
  • Metering (import/export, half-hourly)
Resources:
  • IET - Grid Connection of Solar PV https://electrical.theiet.org/
  • RenewableUK - Wind Energy https://www.renewableuk.com/

UK Grid Code Compliance (G99/G100)

UK requirements for connecting generation to distribution networks. Engineering Recommendation G99 classifications, technical requirements, and the connection application process.

Prerequisites: How Renewables Connect to the Grid
You'll learn to:
  • Classify generators by G99 type
  • Understand key technical requirements
  • Navigate UK connection application process
G99 Overview

Engineering Recommendation G99 (replaced G59 in 2019)

Aligns UK with EU Requirements for Generators (RfG).

Applies to all new generation connecting to distribution networks (up to 132kV).

Key document: ENA Engineering Recommendation G99

Generator Classification

Based on capacity and connection voltage:

Type Capacity Voltage Requirements
A 0.8kW - 1MW <110kV Basic
B 1 - 10 MW <110kV Intermediate
C 10 - 50 MW <110kV Advanced
D ≥50 MW or ≥110kV Any Full compliance

Higher types have more onerous requirements.

Key Technical Requirements

Frequency response:

  • LFSM-O: Reduce output above 50.4Hz
  • LFSM-U: Maintain output down to 47.5Hz
  • FSM: Optional fast frequency response

Voltage ride-through:

  • Must stay connected during voltage dips
  • Type-dependent duration and depth

Reactive capability:

  • Power factor range (typically 0.95 lag to 0.95 lead)
  • Voltage control modes

Protection settings:

  • Over/under frequency and voltage
  • Rate of Change of Frequency (RoCoF)
  • Vector shift (Loss of Mains)
G100 - Export Limiting

G100 allows connection where network capacity is limited.

Active Network Management (ANM):

  • Real-time curtailment signals
  • Generator reduces output when network constrained
  • Enables more DG without reinforcement

Principle of Access:

  • Last-in, first-off (LIFO)
  • Or pro-rata sharing
Connection Process

Steps to connect:

  1. Application: Submit G99 form A to DNO
  2. Assessment: DNO studies impact (4-12 weeks)
  3. Offer: Connection offer with costs and timescales
  4. Acceptance: Sign agreement, pay charges
  5. Design: Detailed design and approval
  6. Construction: Install equipment
  7. Commissioning: Witness tests, settings verification
  8. Energisation: Final Operating Notification (FON)

Typical timescales: 3-18 months depending on complexity

Resources:
  • ENA - Engineering Recommendations https://www.energynetworks.org/
  • National Grid ESO - Grid Code https://www.neso.energy/industry-information/codes/

Voltage Rise from Embedded Generation

How distributed generation causes voltage rise on distribution networks, calculation methods, and mitigation strategies. A key constraint on DG hosting capacity.

Prerequisites: UK Grid Code Compliance (G99/G100)
You'll learn to:
  • Calculate voltage rise from DG connections
  • Understand R/X ratio effects at different voltage levels
  • Design mitigation strategies
The Voltage Rise Problem

Traditional networks designed for one-way power flow:

Substation → Feeder → Loads
(Voltage drops along feeder)

With DG, power can flow backwards:

Substation ← DG export
(Voltage rises at DG location)

Voltage may exceed statutory limits (+10% / -6% in UK).

Voltage Rise Formula

Approximate voltage change from injected power:

ΔV≈P⋅R+Q⋅XV\Delta V \approx \frac{P \cdot R + Q \cdot X}{V}ΔV≈VP⋅R+Q⋅X​

Where:

  • P, Q = active/reactive power injection
  • R, X = resistance/reactance to source
  • V = nominal voltage

In per-unit:

ΔVpu≈Ppu⋅Rpu+Qpu⋅Xpu\Delta V_{pu} \approx P_{pu} \cdot R_{pu} + Q_{pu} \cdot X_{pu}ΔVpu​≈Ppu​⋅Rpu​+Qpu​⋅Xpu​

R/X Ratio Effect
Network R/X Ratio Dominant Factor
LV (400V) 2-5 Active power (P)
11kV 1-2 Both P and Q
33kV 0.3-0.5 Reactive power (Q)
132kV 0.1-0.2 Reactive power (Q)

Key insight: At LV, voltage rise mainly from real power export.

Reactive power absorption has limited effect on LV voltage.

UK Voltage Limits

Statutory limits (ESQCR):

  • LV: 230V +10% / -6% (216V to 253V)
  • HV: ±6% of nominal

DNO planning limits (more conservative):

  • Typically allow +3% rise from DG at minimum load
  • Ensures headroom for voltage regulation
Mitigation Strategies

Network solutions:

  • Conductor upgrades (reduce R)
  • New transformer (reduce impedance)
  • Voltage regulators / boosters

DG solutions:

  • Reactive power absorption (Q negative)
  • Power factor control (limited at LV)
  • Active power curtailment
  • Export limiting (G100)

Smart solutions:

  • OLTC coordinated control
  • Active Network Management (ANM)
  • Battery storage for peak shaving
Resources:
  • IET - Voltage Rise Calculations https://electrical.theiet.org/
  • Western Power Distribution - DG Connections https://www.nationalgrid.co.uk/

Anti-Islanding Protection

Preventing distributed generation from energising an isolated section of network. Detection methods, protection settings, and UK requirements for Loss of Mains protection.

Prerequisites: Voltage Rise from Embedded Generation
You'll learn to:
  • Explain islanding hazards
  • Specify anti-islanding protection settings
  • Design Loss of Mains protection schemes
What is Islanding?

Grid connection with storage

Image: Wikimedia Commons, CC BY-SA 4.0

Islanding: DG continues to energise a section of network that has been disconnected from the main grid.

Can occur when:

  • Upstream breaker opens (fault, maintenance)
  • DG output matches local load (balanced island)
Islanding Hazards

Safety:

  • Network assumed dead may be live
  • Risk to personnel working on "isolated" network
  • Public contact with downed conductors

Equipment:

  • Poor power quality (voltage/frequency drift)
  • Out-of-phase reclosing (severe damage)
  • Fault clearance failure (no grid fault current)

Requirement: Disconnect within 2 seconds of island forming.

Passive Detection Methods

Detect abnormal conditions caused by islanding:

Method Setting Notes
Under-voltage (27) 0.8 pu 0.5s delay
Over-voltage (59) 1.1 pu 1.0s delay
Under-frequency (81U) 47.5 Hz 0.5s delay
Over-frequency (81O) 52 Hz 0.5s delay
RoCoF (81R) 1.0 Hz/s 0.5s delay
Vector Shift (VS) 6° Instantaneous

Limitation: May not detect balanced island (generation = load).

Active Detection Methods

Inverter deliberately perturbs output to detect island:

Frequency shift: Slight bias causes runaway if islanded

Reactive power variation: Inject Q pulses, monitor V response

Impedance measurement: Inject signal, measure grid impedance

More reliable than passive methods but can interact between multiple inverters.

UK G99 Requirements

Loss of Mains (LoM) protection settings:

Protection Setting Delay
Under-frequency 47.5 Hz 0.5s
Over-frequency 52.0 Hz 0.5s
Under-voltage 0.8 pu 2.5s
Over-voltage 1.1 pu 1.0s
RoCoF 1.0 Hz/s 0.5s

Note: RoCoF settings relaxed from 0.125 Hz/s to 1.0 Hz/s to improve stability with low inertia.

Vector shift generally not used in UK (nuisance tripping).

Interface Protection Panel

G99-compliant protection relay provides:

  • Voltage and frequency protection (27, 59, 81)
  • RoCoF protection (df/dt)
  • Intertrip receive (from DNO)
  • Status monitoring and event logging

Must be type-tested to G99 requirements.

Common manufacturers: Woodward, Schneider, ABB, Siemens

Resources:
  • ENA - Loss of Mains Protection https://www.energynetworks.org/
  • IEEE 1547 - DG Interconnection https://standards.ieee.org/

UK Power System

UK Network Structure

Organisation of the GB electricity system: the system operator (NESO), transmission owners, and distribution network operators. Understanding roles, responsibilities, and regulatory framework.

Prerequisites: Anti-Islanding Protection
You'll learn to:
  • Identify roles of NESO, transmission owners, and DNOs
  • Understand UK regulatory framework
  • Navigate industry organisation structure
GB System Overview

UK National Grid map

Image: Wikimedia Commons, CC BY-SA 3.0

Great Britain has a unified synchronous grid covering England, Wales, and Scotland.

Northern Ireland is part of the all-island Irish system (connected via HVDC).

Key principle: Separation of system operation from asset ownership.

National Energy System Operator (NESO)

NESO (formerly National Grid ESO, separated October 2024)

Role: Balances supply and demand in real-time

Responsibilities:

  • Frequency control (maintain 50Hz ± 0.5Hz)
  • Voltage management
  • Constraint management
  • Balancing mechanism operation
  • Future Energy Scenarios (FES)
  • Network planning and connections

Not an asset owner - operates the system impartially.

Transmission Owners (TOs)

Own and maintain the high-voltage transmission network:

TO Area Voltages
NGET England & Wales 275kV, 400kV
SP Transmission Southern Scotland 132kV, 275kV, 400kV
SHET (SSE) Northern Scotland 132kV, 275kV

Note: 132kV is transmission in Scotland, distribution in England & Wales.

Regulated by Ofgem under RIIO-T2 price control.

Distribution Network Operators (DNOs)

Own and operate local distribution networks:

DNO Group Operating Areas
UK Power Networks London, East, South East
National Grid ED Midlands, South West, South Wales
SP Energy Networks Merseyside, North Wales, Central/Southern Scotland
SSE Networks Northern Scotland, Southern England
Northern Powergrid North East, Yorkshire
Electricity North West North West England

14 licensed DNO areas across GB.

Regulated under RIIO-ED2 price control.

Regulatory Framework

Ofgem: Independent regulator

  • Sets price controls (allowed revenues)
  • Enforces licence conditions
  • Protects consumer interests

ELEXON: Settlement body

  • Balancing and Settlement Code (BSC)
  • Calculates imbalance charges

Energy Networks Association (ENA):

  • Industry body for network operators
  • Publishes Engineering Recommendations (G99, P28, etc.)
Resources:
  • National Grid ESO - About Us https://www.neso.energy/
  • Ofgem - Network Regulation https://www.ofgem.gov.uk/

UK Voltage Levels

Standard voltage levels used in the GB power system from 400kV transmission down to 230V consumer supply. Understanding the hierarchy and interface points between networks.

Prerequisites: UK Network Structure
You'll learn to:
  • Identify UK voltage levels and their applications
  • Understand substation hierarchy and interface points
  • Select appropriate voltage for different connections
Transmission Voltages

Supergrid (England & Wales):

  • 400kV - Main bulk transmission
  • 275kV - Older transmission, some areas

Scotland:

  • 400kV, 275kV - Main transmission
  • 132kV - Transmission (not distribution)

Interconnectors:

  • HVDC links to France, Netherlands, Belgium, Norway, Ireland
  • Typically ±320kV to ±525kV DC
Distribution Voltages
Voltage Name Typical Use
132kV EHV (E&W only) Grid Supply Points, large industrial
33kV HV Primary distribution, bulk supply
11kV HV Secondary distribution, commercial
6.6kV HV Some older urban networks
400V LV (3-phase) Commercial, small industrial
230V LV (1-phase) Domestic consumers

Note: Some areas have 20kV or 22kV instead of 11kV.

Interface Points

Grid Supply Point (GSP):

  • Transmission to distribution interface
  • 400kV/275kV → 132kV (or 33kV in some areas)
  • Metering point for settlement

Bulk Supply Point (BSP):

  • 132kV → 33kV transformation
  • Feeds multiple primary substations

Primary Substation:

  • 33kV → 11kV transformation
  • Feeds HV distribution network

Secondary Substation (Distribution):

  • 11kV → 400V transformation
  • Pole-mounted or ground-mounted
  • Feeds LV network to consumers
Substation Diagram

Typical voltage hierarchy:

400kV ──┬── GSP
        │
132kV ──┼── BSP
        │
 33kV ──┼── Primary
        │
 11kV ──┼── Secondary
        │
400V ───┴── Consumer

Each step typically has 2-3 transformers for redundancy.

Nominal vs Declared Voltage

Nominal voltage: System design voltage (e.g., 11kV, 400V)

Declared voltage: What supplier declares to customers

  • LV: 230V (was 240V until 1995 harmonisation)
  • Tolerance: +10% / -6% (216V to 253V)

Historical note: UK moved from 240V ±6% to 230V +10%/-6%, effectively the same range but aligned with European standard.

Resources:
  • ENA - Electricity Networks Overview https://www.energynetworks.org/
  • National Grid - Network Route Maps https://www.nationalgrid.com/

UK Standards and Engineering Recommendations

Key technical standards governing UK power system design and operation. Engineering Recommendations for connections, power quality, and planning standards.

Prerequisites: UK Voltage Levels
You'll learn to:
  • Apply relevant Engineering Recommendations to projects
  • Assess power quality compliance (flicker, harmonics, unbalance)
  • Navigate UK connection requirements
Engineering Recommendations Overview

Engineering Recommendations (ERECs) published by ENA:

Industry-agreed technical standards for:

  • Generator connections (G-series)
  • Power quality (P-series)
  • Design and planning (various)

Not legally binding but effectively mandatory via DNO connection agreements.

G99 - Generator Connections

G99: Requirements for connection of generation equipment

Replaced G59 (large) and G83 (small) in April 2019.

Scope: All generation 0.8kW to 50MW connecting at <110kV

Key requirements:

  • Frequency and voltage ride-through
  • Reactive capability
  • Protection settings (LoM, over/under V & f)
  • Compliance process and testing

See earlier topic on G99 for details.

G100 - Export Limiting

G100: Technical requirements for export limiting schemes

Allows connection where network capacity limited:

  • ANM (Active Network Management): Real-time curtailment
  • Export limiting: Fixed maximum export
  • Timed connections: Export only at certain times

Enables more DG without costly reinforcement.

P28 - Voltage Fluctuations

P28: Planning limits for voltage fluctuations

Flicker: Rapid voltage variations causing visible light flicker

Limits:

  • Short-term severity Pst≤1.0P_{st} \leq 1.0Pst​≤1.0
  • Long-term severity Plt≤0.8P_{lt} \leq 0.8Plt​≤0.8
  • Step changes ≤3%\leq 3\%≤3% (frequent) or 6% (infrequent)

Causes: Motor starting, arc furnaces, wind turbines

Assessment: Required for large loads or generation connections

P29 - Voltage Unbalance

P29: Planning limits for voltage unbalance

Unbalance: Difference between phase voltages

VUF=V2V1×100%\text{VUF} = \frac{V_2}{V_1} \times 100\%VUF=V1​V2​​×100%

Where V2V_2V2​ = negative sequence, V1V_1V1​ = positive sequence

Limits:

  • Planning level: 1.3%
  • Compatibility level: 2.0%

Causes: Single-phase loads, unbalanced three-phase loads

G5 - Harmonics

G5/4-1: Planning levels for harmonic voltage distortion

THD (Total Harmonic Distortion):

THD=∑h=240Vh2V1×100%THD = \frac{\sqrt{\sum_{h=2}^{40} V_h^2}}{V_1} \times 100\%THD=V1​∑h=240​Vh2​​​×100%

Planning limits (% of fundamental):

Voltage THD Individual (odd)
LV 5% 4-5%
MV (11-33kV) 4% 3-4%
HV (132kV) 3% 2-3%

Causes: Power electronics, VFDs, rectifiers, LED lighting

Other Key Standards

Security standards:

  • SQSS: Security and Quality of Supply Standard (transmission)
  • P2/6: Security of supply (distribution) - being replaced by P2/8

Design standards:

  • BS 7671: Wiring Regulations (LV installations)
  • ENA TS 41-24: Guidelines for LV connections

Grid codes:

  • Grid Code: Transmission-connected parties
  • Distribution Code: Distribution-connected parties
  • CUSC: Connection and Use of System Code
Resources:
  • ENA - Engineering Recommendations https://www.energynetworks.org/industry-hub/resource-library
  • National Grid ESO - Grid Code https://www.neso.energy/industry-information/codes/grid-code

UK System Operation Basics

How the GB electricity system is balanced in real-time. Understanding frequency control, the balancing mechanism, and constraint management.

Prerequisites: UK Standards and Engineering Recommendations
You'll learn to:
  • Explain how system frequency is maintained
  • Understand the balancing mechanism basics
  • Describe constraint management approaches
Frequency Control

Target: 50.00 Hz ± 0.2 Hz (normal operating range)

Frequency rises when generation > demand Frequency falls when demand > generation

Response services:

Service Speed Duration
Inertia Instantaneous Seconds
Primary response 10 seconds 30 seconds
Secondary response 30 seconds 30 minutes
Tertiary / reserve Minutes Hours

NESO procures these services from generators and batteries.

Balancing Mechanism

BM: Real-time market for balancing

How it works:

  1. Generators/suppliers submit bids and offers
  2. Bid: Price to reduce output (or increase demand)
  3. Offer: Price to increase output (or reduce demand)
  4. NESO accepts bids/offers to balance system
  5. Settled at bid/offer price (pay-as-bid)

Gate closure: 1 hour before delivery

Imbalance price: Cash-out for parties not in balance

Constraint Management

Constraint: When power flow exceeds line/transformer rating

Causes:

  • High renewable output in weak areas
  • Outages reducing network capacity
  • Demand patterns

Actions:

  • Re-dispatch generation (BM actions)
  • Curtail wind/solar
  • Intertrips (automatic post-fault)

Constraint costs: £500M+ annually (growing with renewables)

Demand Forecasting

NESO forecasts demand to plan generation:

Timescales:

  • Week ahead: Unit commitment
  • Day ahead: Final schedules
  • Intraday: Adjustments
  • Real-time: Balancing actions

Factors:

  • Weather (temperature, wind, solar)
  • Time of day/week/year
  • TV pickups (kettles at half-time!)
  • Bank holidays
  • COVID showed how much patterns can change
Future Challenges

System operation becoming more complex:

Low inertia:

  • Less synchronous generation
  • Faster frequency changes
  • Need for synthetic inertia from batteries/IBRs

Variable renewables:

  • High instantaneous penetration (>70% at times)
  • Need for flexibility (storage, DSR, interconnectors)

Distributed resources:

  • Millions of small generators/batteries
  • Visibility challenge for NESO
  • Local vs national balancing
Resources:
  • National Grid ESO - Balancing Services https://www.neso.energy/industry-information/balancing-services
  • ELEXON - Imbalance Pricing https://www.elexon.co.uk/
  • Grid Watch - Live GB Grid Data https://gridwatch.co.uk/